LUGE PARK DEVELOPMENT

LUGE PARK

DEVELOPEMENT PROCESS

To create a luge park, a overall plan must be prepared after selecting a project site and reviewing the business feasibility.

After that, detailed design and government permission are completed, and construction begins.

At each stage, design and construction must be carried out in consideration of passenger safety and efficient traffic lines.

INCREX offers consulting service based on various project experiences.

Phase 1

BASIC PLANNING

Two months' time

· Finding and selecting possible site

· Overall track design

· Transportation system

· Feasibility study

· Environment impact assessment and government permission

· Master plan

Phase 2

DETAILED PLANNING

Three months' time

· Detailed track design

· Passenger and staff path planning

· Lift transportation system design

· Detailed civil engineering design

Phase 3

CONSTRUCTION

Six months' time

· Overall civil construction

· Luge track construction

· Entrance and parking lot

· Gondola or lift installation

Phase 4

LUGE SUPPLY

a months' time

· Luge cart preparation

· Training of repair and maintenance

· Tool sets and repair manual

· Training of staffs

INCREX inc.


T. 82 31 687 8299  |  www.increx.co.kr

HQ. #521, 118, LS-ro 116 Beon-gil, Dongan-gu, Anyang-si, Gyeonggi-do, South Korea

CN Factory. No 15, Jinchuan Road, Beicheng sub-district, Huangyan, Taizhou, Zhejiang, China

INCREX inc.  |  Luge Cart Division


T. 82 31 687 8299  |  info@lugecart.co.kr

HQ. #521, 118, LS-ro 116 Beon-gil, Dongan-gu, Anyang-si, Gyeonggi-do, South Korea

CN Factory. No 452, Xinjiang Road, Xinqian, Huangyan, Taizhou, Zhejiang, China